Scupper 98

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – (Ongoing)

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

March 12, 2019

Scupper 98

Tuesday

I spent the morning hours applying the first coat of semi-gloss white enamel to all interior surfaces in the forward and main cabins.  While it appears glossy in the just-applied photos, the paint would cure to a pleasing soft sheen.

Next, I applied a coat of the enamel to the top sides of the various loose locker lids.

During the afternoon, I sanded all the newly-milled trim pieces, working through the grits from 80 to 220 to remove tool marks and smooth the wood to prepare for finishing.

Total time billed on this job today:  7.5 hours

0600 Weather observation:  26°, mainly clear.  Forecast for the day: Partly sunny, 37°