Scupper 1

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  651.25

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
Beginning in Fall 2019

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

September 13, 2017

Scupper 1

< Back to Scupper

Shortly after arrival at the shop in June 2017, I performed a walk-through and visual inspection of the boat to observe her overall condition and help determine, along with the owner’s eventual input, the project scope ahead.  The boat, a unique design called a Mystic Legnos 30, was in pretty rough shape overall, with substantial cosmetic requirements as well as the usual collection of deck problems and old systems.

Click here to view numerous photos and the initial inspection report.

Though I didn’t expect to begin the substantial portion of the project for some months, with some availability in the schedule and shop I took the opportunity to move Scupper indoors and begin some of the preliminary work, mainly cleaning out and the beginnings of disassembly and hardware removal.

Once she was indoors, I spent part of a day removing various items from the cabin and storage areas.  More work to come.

Total time billed on this job today:  3 hours