Scupper 162

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  651.25

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – (Ongoing)

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

October 18, 2019

Scupper 162

Friday

Before getting back to work on Scupper for the final phase of the project, I chose to relocate the boat in the shop bay.  During the interior work, and to accommodate another project in the bay, I’d moved the boat far over to one side of the shop, but now I needed her back in the center of the bay to provide access to all sides of the boat for staging and upcoming exterior paint work.

Thusly positioned, I continued by installing the staging at deck height so I could get to work on a few final details before moving into priming and painting.

Total time billed on this job today:   2 hours

0600 Weather Observation:  45°, mainly cloudy.  Forecast for the day:  Partly cloudy, 50°