Scupper 116

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  651.25

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – (Ongoing)

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

April 4, 2019

Scupper 116

Thursday

The various small trim pieces and panel fronts I’d treated with the satin varnish cured well, and to all appearances were complete.

For the remaining trim underway in the boat, I went through the usual processes of sanding, vacuuming, solvent wash, etc. before applying another round of gloss base varnish to all areas.  Unfortunately, this was all I had time for this day.

Total time billed on this job today:  2 hours

0600 Weather observation:  30°, clear,   Forecast for the day:  Sunny and windy, 42°