Scupper 55

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – (Ongoing)

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

August 16, 2018

Scupper 55

< Back to Scupper

Thursday

I spent the morning working on the final details of pre-primer prep, including setting up spray gun equipment, pre-stirring the always-settled paint cans, final deck and hull preparations including tack-off, and other related tasks.

Next:  high build primer.

Total time billed on this job today:  2.5 hours

0600 Weather Observation:  Mostly cloudy and low fog, 68°.  Forecast for the day:  Partly sunny, 82°