Scupper 177

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  651.25

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – (Ongoing)

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

November 7, 2019

Scupper 177

Thursday

After final preparations, I spray-applied three coats of Alexseal snow white topcoat to all deck areas, working as usual in two stages and over the course of several elapsed hours:  First the inboard areas of the coachroof and cockpit, including the cockpit well; and then all the remaining areas, including cabin trunk, channels, coamings, and the outer areas of the cockpit.

Total time billed on this job today:  5 hours

0600 Weather Observation:  32°, cloudy. Forecast for the day:  Cloudy with rain likely in the afternoon, 45°