Scupper 58

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  651.25

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
Back to work on October 21, 2019

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

August 20, 2018

Scupper 58

< Back to Scupper

Monday

Continuing on the hull, I worked during the morning to sand the starboard side with 220 grit, smoothing the fresh primer.

After resetting the staging so I could reach the decks again, I finished up the work on deck, sanding the foredeck, sidedecks, poop deck, and cabin trunk/outer coamings as needed to smooth the primer.

Total time billed on this job today:  7 hours

0600 Weather Observation:  50°, clear.  Forecast for the day:  Sunny, 75°