Scupper 60

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – (Ongoing)

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

August 22, 2018

Scupper 60

< Back to Scupper

Wednesday

The fine fairing compound had cured overnight, and now I sanded it smooth with 220 grit, removing the excess.  A few of the tight corners in the cockpit, including the locker lid gutters and other select areas, would require some additional hand-sanding work in the near future, as during this session I avoided getting bogged down with detail-oriented hand work in favor of the broad strokes of the bulk of the deck surface.

Total time billed on this job today:  4 hours

0600 Weather Observation:  64°, cloudy.  Forecast for the day:  Clouds, rain and possible thunderstorms developing, 70s