Scupper 182

Boat:

Scupper, a 1978 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  651.25

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – (Ongoing)

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

November 14, 2019

Scupper 182

Thursday

Now that the topsides paint had had adequate cure time, I worked to mask off the hull so I could spray the boottop.  I started with a narrow strip of vinyl fine-line tape to define the top edge of the stripe, then covered nearly all the vinyl tape with a strip of regular masking tape.

Afterwards, I covered the hull in plastic and masking paper above the boottop to protect against overspray.

After final preparations, including solvent-washing and tacking off the boottop, I applied three coats of Alexseal Toreador red to the stripe, leaving things to cure overnight.

Total time billed on this job today:  4.5 hours

0600 Weather Observation:  6°, mainly clear (high clouds).  Forecast for the day:  Mainly cloudy, chance of snow showers, 33°