Scupper 113

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

This project is being completed in several phases over two years to meet the owner’s schedule.

Early Phase:  Hardware removal and early assessment
September 2017

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  341.75

Phase 2: Interior, systems, and more
January 23, 2019 – (Ongoing)

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

April 1, 2019

Scupper 113

Monday

My first task of the day was to lightly sand and varnish once more the small trim pieces I’d been working on.

My immediate focus was to prepare the new trim in the boat for its own varnish coats, so I spent most of the morning on that task, including removing excess bungs from the newest trim, lightly sanding all the bungs and trim, and masking off everything as needed.  I also permanently installed the fiddle on the now-complete plywood v-berth filler piece so I could complete the varnish on that trim as well.  With one coat possible per day, I hoped to finish up the varnish work during the course of the week and weekend.

I’d planned to apply the varnish right after lunch, wanting to ensure its completion but unsure how long it would take, but was called away unexpectedly and unable to return in time to complete the work I’d planned.

Total time billed on this job today:  4.5 hours

0600 Weather observation:  25°, clear.   Forecast for the day:  Sunny and windy, 37°