Scupper 71

Boat:

Sea Breeze (FKA Scupper), a 1978 Legnos Mystic 30' Cutter

Schedule:

This project was completed in several phases over two years to meet the owner’s schedule.

Initial Pre-Project Inspection Report and Observations

Early Phase:  Hardware removal and early assessment
September 2017
Early Phase Hours:  26.75

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  315

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  665.5

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – March 27, 2020
Phase 3 Hours:  683.75

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Project Complete:  1691 Total Hours

 

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

February 1, 2019

Scupper 71

Friday

After sanding the second round of hole filler in the cabin, I found many of the spots weren’t yet smooth and flush, so I was required to apply an additional coat of the filler throughout the cabin.  I had hoped to avoid this, but fortunately the white acrylic filler would cure quickly and I’d be able to get back to it later in the day.

While I left those spots to cure, I prepared to install various fiberglass patches throughout the interior, including the old deck prism openings and some cracks in the forward part of the liner, as well as three remaining through hull locations–the galley sink, head sink, and an old depth transducer location in the port settee locker–that I’d previously filled and patched from outside, but hadn’t yet patched from within because when I did some of the other patches earlier in the project, I’d yet to sand and prepare the inside of the hull in these other areas.

After cutting the new fiberglass for all areas, and other final preparations, I wet out with epoxy and installed all the patches.

To finish off the forward hatch frame installation, I installed narrow strips of fiberglass over the inside of the opening, extending from the new fiberglass frame down over the exposed core and deck structure.  I let the pieces hand down a bit over the gap between the deck and the interior liner, but did not attempt to incorporate the liner into the system.  The fiberglass would add some strength and also sealed off the exposed core; all this would later be hidden with trim.

By now, the putty over the holes in the cabin liner had cured, and I performed what I hoped was the final sanding of all areas.

To finish up the day, I continued work on the rudder, beginning with sanding and cleaning up the second round of reconstructive structural epoxy.

Afterwards, I built up the bottom edge just a bit more as needed, focusing mainly on the after corner where I wanted a “squarer” rounded shape.  By now, the shape was looking pretty close to what I was going for, and I expected one final round of minor shaping and smoothing to fine-tune the rudder before I could finish up with new fiberglass.

Total time billed on this job today:  6.75 hours

0600 Weather Observation:  -4°, clear.  Forecast for the day:  Sunny, 20°