Scupper 36

Boat:

Sea Breeze (FKA Scupper), a 1978 Legnos Mystic 30' Cutter

Schedule:

This project was completed in several phases over two years to meet the owner’s schedule.

Initial Pre-Project Inspection Report and Observations

Early Phase:  Hardware removal and early assessment
September 2017
Early Phase Hours:  26.75

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  315

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  665.5

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – March 27, 2020
Phase 3 Hours:  683.75

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Project Complete:  1691 Total Hours

 

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

May 2, 2018

Scupper 36

< Back to Scupper

Wednesday

To get started, I installed the two layers of biaxial tabbing on the starboard hull/deck joint, repeating the process I’d completed on the port side earlier.

After a break for a few hours while I completed some work on another project getting ready to leave the shop later in the week, I lightly sanded the new fiberglass on the port gunwale to prepare it for fairing.

After cleaning up, I installed two layers of tabbing over the taffrail/transom section of the hull/deck joint.  Here, I required shorter sections to better approximate the curvature of the seam.

Finally, I applied the first coat of epoxy fairing compound to the port gunwale, beginning to smooth the new work in to the existing surfaces of hull and deck.  For now, I focused on filling the edge between the top layer of tabbing and the existing surfaces, and filled the weave of the cloth in the remaining areas.

Total time billed on this job today:  5.25 hours

0600 Weather Observation:  40°, clear.  Forecast for the day:  Sunny, 80s