Scupper 31

Boat:

Sea Breeze (FKA Scupper), a 1978 Legnos Mystic 30' Cutter

Schedule:

This project was completed in several phases over two years to meet the owner’s schedule.

Initial Pre-Project Inspection Report and Observations

Early Phase:  Hardware removal and early assessment
September 2017
Early Phase Hours:  26.75

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  315

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  665.5

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – March 27, 2020
Phase 3 Hours:  683.75

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Project Complete:  1691 Total Hours

 

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

April 20, 2018

Scupper 31

< Back to Scupper

Friday

After removing the core weights and other preparations, I lightly sanded the newly-cored areas to remove any epoxy ridges or overspill, and sanded the new fiberglass top skins on the smaller repairs I’d made earlier.  I’d also applied some filler to the small depression in the bottom skin near the forward end of the port sidedeck, and lightly sanded that as well.

In my usual way, I made paper patterns for the fiberglass needed for the bridgedeck and coachroof, and cut out two layers of 1708 fiberglass for each section.

I filled any small gaps remaining around the new core with a thickened epoxy mixture, and after letting that sit while  I cut out the new fiberglass, I laminated both areas with the two new layers.

I dry fit the new core pieces on the port sidedeck, made a couple minor adjustments, and then installed the new core in thickened epoxy adhesive, weighing it all down securely.

In the cockpit, I filled the large hole left over from the steering pedestal, then installed the two layers of fiberglass over the top of the whole area that I’d prepared earlier.  I also filled and patched the old fuel tank fill hole on the poop deck.  Later, once I’d shifted operations belowdecks, I’d complete these two patches from the underside.

Finally, picking up where I’d left off before, I finished up the initial filling of the hull-deck joint on the starboard side, and applied a second round of filler as needed to some of the previously-filled areas on the port side.

Total time billed on this job today:  7.5 hours

0600 Weather Observation:  34°, drizzle.  Forecast for the day:  Clouds, showers, maybe some sun, around 50°