Scupper 232

Boat:

Sea Breeze (FKA Scupper), a 1978 Legnos Mystic 30' Cutter

Schedule:

This project was completed in several phases over two years to meet the owner’s schedule.

Initial Pre-Project Inspection Report and Observations

Early Phase:  Hardware removal and early assessment
September 2017
Early Phase Hours:  26.75

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  315

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  665.5

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – March 27, 2020
Phase 3 Hours:  683.75

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Project Complete:  1691 Total Hours

 

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

January 31, 2020

Scupper 232

Friday

Easing into the day with a simple yet necessary task, I installed the four pulpit brackets that would support the lower lifeline attachments.

The cabin top was ready for the final installation of the new hardware, so to begin I drilled, tapped, and countersunk all the fastener holes for the winch, rope clutch, and fairlead.

Belowdecks, I marked and cut away the liner in way of the winch and rope clutch, and drilled two 1-1/2″ holes with a hole saw at the fairlead fastener locations.  This exposed the underside of the deck proper.  For the winch and rope clutch, I prepared backing plates from fiberglass sheeting to fit in the new openings.

I began the installation with the fairlead, which was furthest forward and the simplest installation overall.  I applied sealant and installed two 1/4″ bolts.  I discovered that I’d cut away the liner from the wrong hole beneath (there are many old holes in the liner), and had to cut a new opening for the inboard fastener on the fly.  These holes accepted large fender washers to secure the fairlead.

Next, I installed the winch base with sealant and six bolts, using the backing plate and fender washers beneath.  There was just enough room so that the backing plate and nuts fit  just flush with the existing liner, which was important since the new overhead panels fit closely to the old liner.

The rope clutch admonished the user not to use polysulfide or polyurethane sealant, and since my standard sealant is a light polyurethane, I used butyl tape instead  to install the rope clutch with its eight bolts, installing the new backing plate and fender washers beneath.

This completed the hardware installation for the aft-led control lines.

Next, I drilled, tapped, and countersunk all the fastener holes for the stern cleats, ladder brackets, and bow cleats.

The varnished wooden backing plates for the bow cleats weren’t yet ready for installation, but I could proceed with the stern cleats after making a pair of fiberglass backing plates to fit.

To gain access to the underside of the deck at the ladder mounts, I had to cut away more of the liner to expose the deck.  I hated to do this, but there was nothing for it, and these new openings were between the existing openings I’d cut for the lifeline stanchions, so when I built trim to cover the cutouts I could simply plan to do it in one fell swoop.

Because I didn’t want a mess of sealant to ooze into the open space of the bracket mounts required for the top of the ladder, I chose butyl tape to seal the brackets, and bolted them in place with large washers beneath.  The ladder fit well on both sides, but I’d have to later trim to length the standoff brackets on the ladder so it would be properly supported by the hull.

With that, and after a bit of boat and shop cleanup, I reached the end of the day’s work.

Total time billed on this job today:  7.25 hours

0600 Weather Observation: 11°, clear. Forecast for the day:  Sunny, 39°