Scupper 171

Boat:

Sea Breeze (FKA Scupper), a 1978 Legnos Mystic 30' Cutter

Schedule:

This project was completed in several phases over two years to meet the owner’s schedule.

Initial Pre-Project Inspection Report and Observations

Early Phase:  Hardware removal and early assessment
September 2017
Early Phase Hours:  26.75

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  315

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  665.5

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – March 27, 2020
Phase 3 Hours:  683.75

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Project Complete:  1691 Total Hours

 

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

October 31, 2019

Scupper 171

Thursday

Before I could start the hull primer, I had to reset the staging to hull height, and once the planks were reconfigured I added a strip of masking paper just below the waterline (which was still masked off from the high-build primer) to protect the bottom against overspray.  Then, I tacked off the hull.

With preparations complete, I spent the remainder of the day applying four coats of the Alexseal epoxy finish primer, sticking with white since the hull would be painted a light color.  I went with four coats to provide good coverage over parts of the hull/deck joint, which was fairly dark even beneath the high-build.

Total time billed on this job today:  4.75 hours

0600 Weather Observation:  58°, cloudy and fog/drizzle . Forecast for the day:  Rain and patchy fog, 64°