Scupper 153

Boat:

Sea Breeze (FKA Scupper), a 1978 Legnos Mystic 30' Cutter

Schedule:

This project was completed in several phases over two years to meet the owner’s schedule.

Initial Pre-Project Inspection Report and Observations

Early Phase:  Hardware removal and early assessment
September 2017
Early Phase Hours:  26.75

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  315

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  665.5

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – March 27, 2020
Phase 3 Hours:  683.75

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Project Complete:  1691 Total Hours

 

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

June 7, 2019

Scupper 153

Friday

The weather forecast suggested that I might have a chance the temperatures I needed to pour the epoxy countertop early in the week, so I continued some of the prep work towards that end, masking off lavishly around the countertop, and using duct tape to dam up the four openings in the countertop (stove, sink, and two storage openings).

With that complete, I sanded the companionway door trim and, after cleanup and all final preparations, applied a coat of the same rubbed-effect satin varnish used everywhere else in the cabin.  Much later, with the varnish cured, I removed the masking tape and rehung the laddor [sic].  Still ahead, I’d prime and paint the remainder of the companionway opening to complete the finishing work.

Total time billed on this job today:   3 hours

0600 Weather Observation:  45°, clear. Forecast for the day:  Sunny, 76°