Scupper 35

Boat:

Sea Breeze (FKA Scupper), a 1978 Legnos Mystic 30' Cutter

Schedule:

This project was completed in several phases over two years to meet the owner’s schedule.

Initial Pre-Project Inspection Report and Observations

Early Phase:  Hardware removal and early assessment
September 2017
Early Phase Hours:  26.75

Phase 1: Dismantling, surface prep, systems removal, repairs, structural work
March 16, 2018 – November 16, 2018 (Discontinuous)
Phase 1 Hours:  315

Phase 2: Interior, systems, and more
January 23, 2019 – June 21, 2019
Phase 2 Hours:  665.5

Phase 3:  Electrical, electric motor, plumbing,  final exterior finishing, and everything else
October 18, 2019 – March 27, 2020
Phase 3 Hours:  683.75

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Project Complete:  1691 Total Hours

 

Begin Daily Project Logs

Alternately, click the button below to navigate to a specific log.

May 1, 2018

Scupper 35

< Back to Scupper

Tuesday

I continued with another round of sanding on the deck areas as needed.

The coachroof would require a fair bit of work going forward, as the existing repairs, while apparently sound, were far from cosmetically acceptable.  As a first step, I had to get rid of the remnants of the old adhesive that had secured the Treadmaster.  In this case, since the existing surface was such a mess and wasn’t remotely fair to begin with, I used a sanding disc on a grinder to quickly remove the worse of the old adhesive and aggressive nonskid paint on the coachroof, taking care not to go too far and leaving behind a skim of paint that I’d remove another time with a less-aggressive tool.

My next main focus was the hull-deck joint.  Now that the port sidedeck was rebuilt, and the first round of fairing applied that had brought the edge to similar contours as the remaining portion of the deck, it was time to get to the fiberglassing.  To prepare, I masked off below the edge of the area I’d prepared on the hull to catch the inevitable drips of resin during the installation, and pre-cut a series of 24″ lengths of 6″ and 4″ biaxial tabbing that I’d use to glass over the joint.

I spent the remainder of the day installing the two layers of fiberglass over the port gunwale, starting at the bow with a couple special pieces that I cut to incorporate a hole repair over the old anchor hawse located near the rail.  I staggered the seams between the two layers by 12″, and, installing two sections at a time, worked my way aft to the transom by the end of the day.

To finish up, I pre-cut a couple special pieces for the starboard side, mainly to fit around the winch island, which would save time in the morning when I wanted to repeat the glassing process on the other side.

Total time billed on this job today:  7.25 hours

0600 Weather Observation:  30°, mostly cloudy.  Forecast for the day:  Clouds and a shower, then becoming sunny, 60°