Scupper 53

Boat:

Scupper, a 1979 Legnos Mystic 30' Cutter

Schedule:

Early phase in September 2017 Hardware removal and early assessment

Phase 1 March 2018 – October 2018:  Dismantling, surface prep, systems removal, repairs, structural work

Phase 2 Coming in Winter 2018-2019:  Interior and more

Scope of Project:  Comprehensive refit, including deck repairs, repower, interior makeover, hull work, and systems

Initial Pre-Project Inspection Report and Observations

Begin Daily Project Logs

July 16, 2018

Scupper 53

< Back to Scupper

Monday

Now that the hatch frame was secured in place, I cleaned up and lightly sanded the area as needed to remove any excess epoxy and otherwise prepare the surfaces for the next steps.

Afterwards, I applied a cosmetic epoxy fillet to the transition between the frame and the deck.  I kept the fillet radius small because the frame itself was nearly flush with the deck amidships, at the height of the crown, and there was no need for a large fillet in any event.  The fillet roughly matched the contour of the top edge of the frame, which I’d eased during construction.

Once the new fillet cured overnight, I water-washed, then lightly sanded as needed to prepare the exterior of the hatch frame for high-build primer, after which I’d complete any further fine-tuning if necessary, along with additional work on the inside of the frame to finish off and better secure the opening from within.

Next:  final hull and deck preparations before high-build primer

Total time billed on this job today:  1 hour

0600 Weather Observation:  62°, fog.  Forecast for the day:  Clearing, 80s