110 Cookson Lane | Whitefield, ME  04353 | 207-232-7600 |  tim@lackeysailing.com

Boat:  Waanderlust, a 1961 Rhodes Swiftsure 33' Sloop


Phase I Project Schedule: 
May 2010 - October 2010
Phase II Project Schedule:
  May 2011 - June 2011 

Phase III Project Schedule:  August 2011 - October 2011
Phase IV Project Schedule:  July 2015 - (Ongoing)

Scope of Phase I:  Hull and deck refinishing; partial deck recore; cabin trunk resheathing; partial interior preparation and refinishing  COMPLETE:  8 October 2010  This is Phase I.

Scope of Phase II:  New engine foundations; new fuel tank; initial engine installation; nonskid paint; build and install wooden deadlight frames and deadlights; miscellaneous    COMPLETE:  27 June 2011  Click here to go to Phase II.

Scope of Phase III:  Final engine installation; systems; deck hardware; interior construction and finishing; eyebrow and toerail; miscellaneous  COMPLETE:  8 October 2011  Click here to go to Phase III.

Scope of Phase IV: 
Deck hardware; engine wiring; miscellaneous items required to prepare for launching and project completion.  Click here to go to Phase IV.
 


Daily Project Diary (Phase I):
 
Click here to begin

Or, click on a date below to go directly to any point in the project.
5/11/10 | 5/13/10 | 5/14/10 | 5/17/10 | 5/19/10 | 5/20/10 | 5/21/10 | 5/24/10 | 5/26/10 | 5/27/10

6/1/10 | 6/3/10 | 6/4/10 | 6/7/10 | 6/8/10 | 6/9/10 | 6/10/10 | 6/21/10 | 6/22/10 | 6/23/10 |
6/25/10
6/28/10 | 6/29/10 | 6/30/10 | 7/1/10 | 7/2/10 | 7/6/10 | 7/7/10 | 7/8/10 | 7/9/10 | 7/10/10 | 7/13/10

7/14/10 | 7/15/10 | 7/19/10 | 7/20/10 | 7/21/10 | 7/22/10 | 7/23/10 | 7/26/10 | 7/27/10 | 7/28/10
7/29/10  |  8/2/10 | 8/3/10 | 8/4/10 | 8/5/10 | 8/6/10 | 8/9/10 | 8/10/10 | 8/11/10 | 8/12/10 | 8/13/10
8/16/10  |  8/17/10 | 8/18/10 | 8/19/10 | 8/20/10 | 8/23/10 | 8/25/10 | 8/26/10 | 8/27/10 | 8/30/10

8/31/10 | 9/1/10 | 9/2/10 | 9/7/10 | 9/8/10 | 9/9/10 | 9/11/10 | 9/12/10 | 9/13/10 | 9/14/10 | 9/15/10
9/16/10 | 9/17/10 | 9/20/10 | 9/21/10 | 9/22/10 | 9/23/10 | 10/4/10 | 10/5/10 | 10/6/10 | 10/7/10 | 10/8/10

----------P H A S E  I  C O M P L E T E---------- 


Waanderlust heads into the shop on May 11, 2010

After Phase I of the Project