Lyra 76

Boat:

Lyra, a 1960 Pearson Triton

Schedule:

Project Schedule:  January 2021 – May 2021

Project Scope:  Interior work; deck hardware; cockpit repairs and refinishing; electrical work; electric motor installation; miscellaneous

Project Complete:  366 Total Hours

Lyra will be back in fall 2021 for Phase 2 of the project.

Begin Daily Project Logs

May 17, 2021

Lyra 76

Monday

Late in the week, the valve for the new through hull in the head arrived ahead of schedule, so I finished up the installation with the valve and hose adapter.

With that, everything was ready for Lyra to depart for a couple weeks at the owner’s home where he’d finish a few chores before launching near the end of the month.

Total time billed on this job today:  n/a 

0600 Weather Observation:  42°, clear.   Forecast for the day:  Sunny, 72°, chance of showers and thundershowers

<Back to Lyra