Boat:

Lyra, a 1960 Pearson Triton

Schedule:

Project Schedule:  January 2021 – May 2021

Project Scope:  Interior work; deck hardware; cockpit repairs and refinishing; electrical work; electric motor installation; miscellaneous

Project Complete:  366 Total Hours

Lyra will be back in fall 2021 for Phase 2 of the project.

Begin Daily Project Logs

April 9, 2021

Lyra 54

Friday

I continued work on the ongoing varnish, with another coat (5) on the locker lid tops, and the 4th coat on the first side of the coamings, and the second coat on the swashboards (both sides).  With the varnish done, I applied a coat of white enamel to the underside of the companionway hatch.

Total time billed on this job today:  1.25 hours

0600 Weather Observation:  Clear, 35°.   Forecast for the day:   Sunny, 65°