Project Schedule:  January 2021 – May 2021

Project Scope:  Interior work; deck hardware; cockpit repairs and refinishing; electrical work; electric motor installation; miscellaneous

Project Complete:  366 Total Hours

Lyra will be back in fall 2021 for Phase 2 of the project.

Begin Daily Project Logs

March 29, 2021

Lyra 48

Monday

With the topcoats complete and amply cured, I began by removing all the masking tape, paper, and plastic from the cockpit and the rest of the boat.

Next, I masked over the fresh paint in the cockpit, following the layout I’d made during my earlier masking rounds but this time to protect the new paint from the nonskid to go in the field areas.

After final cleanup and preparations, I applied the first of two coats of light gray nonskid paint to these areas, leaving it to cure during the day while I worked on other projects.

Total time billed on this job today:  2.5 hours