Lyra 43

Boat:

Lyra, a 1960 Pearson Triton

Schedule:

Project Schedule:  January 2021 – May 2021

Project Scope:  Interior work; deck hardware; cockpit repairs and refinishing; electrical work; electric motor installation; miscellaneous

Project Complete:  366 Total Hours

Lyra will be back in fall 2021 for Phase 2 of the project.

Begin Daily Project Logs

March 22, 2021

Lyra 43

Monday

During the first part of the morning, I finished up various final prepwork for the primer and paint stage ahead, including some additional masking (mainly some additional paper to protect the hull around the stern quarters of the boat), plus setup of  paint and spray equipment as needed.  Once all the related preparations were complete, I finished up with a final solvent wash in the cockpit, this time using the paint system’s proprietary solvent for the purpose.

Then, over the course of a few elapsed hours, I applied three coats of epoxy-based high-build primer to the cockpit areas.

Total time billed on this job today:  4.5 hours

0600 Weather Observation:  23°, clear.  Forecast for the day:   Sunny, 60°