Boat: Kaholee, a 1960 Pearson Triton
28' sailboat (Hull # 158) PHASE 1 of 3 Phase 1:
Complete.
Click here for more.
Phase 2:
Complete. Click here for more.
Final Phase:
Complete. Click here for more.
Scope of Project: Kaholee's owner
brought her here all the way from New Mexico so that we could refinish and refit
the boat for extended liveaboard cruising beginning in 2008. Some of the contracted jobs
include:
Phase I (December 2006 - April
2007)
- Rebuild and reconfigure the interior
- Remove Atomic 4
- Replace and refit deck and sailing hardware
- Refinish the decks
- Replace all exterior woodwork
Phase I is completed as of April
20, 2007. More to come in Phase II.
I have prepared these pages so that the
owner can follow along with the progress, but if you've found them,
please enjoy the progress!
Phase I Project Diary:
Click here to begin.
Phase II Project Diary:
Click here
Final Phase:
Click here
Or, click on a date below to go directly to any
point in the project. This is Phase I.
12/04/06 |
12/05/06 |
12/07/06 |
12/11/06 |
12/12/06 |
12/13/06 |
12/14/06 |
12/18/06 |
12/19/06
12/20/06 |
12/21/06 |
1/2/07 |
1/3/07 |
1/4/07 |
1/5/07 |
1/8/07 |
1/9/07 |
1/10/07 |
1/11/07
1/12/07 |
1/16/07 |
1/17/07 |
1/19/07 |
1/22/07 |
1/23/07 |
1/24/07 |
1/25/07 |
1/26/07 |
1/29/07
1/30/07 |
1/31/07 |
2/1/07 |
2/2/07 |
2/3/07 |
2/5/07 |
2/6/07 |
2/7/07 |
2/8/07 |
2/9/07 |
2/10/07
2/11/07 |
2/12/07 |
2/13/07 |
2/14/07 |
2/19/07 |
2/20/07 |
2/21/07 |
2/22/07 |
2/23/07 |
2/26/07
2/27/07 |
2/28/07 |
3/1/07 | 3/2/07 |
3/5/07 | 3/6/07
| 3/7/07 | 3/8/07 |
3/9/07 |
3/12/07 |
3/13/07
3/14/07
| 3/15/07 |
3/16/07 |
3/19/07 |
3/20/07 |
3/21/07 |
3/22/07 |
3/23/07 |
3/24/07 |
3/26/07
3/27/07
| 3/28/07 |
3/29/07 |
3/30/07 |
3/31/07 |
4/2/07 |
4/3/07 | 4/4/07 |
4/5/07 |
4/6/07
4/9/07 |
4/10/07 |
4/11/07 |
4/12/07 |
4/13/07 |
4/16/07 |
4/17/07 |
4/18/07 |
4/19/07 |
4/20/07 |
4/22/07
What's Coming in Phase II
|