Complete miscellaneous
interior trim (see specifics below)
Mill and install teak cabin
sole with black epoxy "caulk" joints
Complete work on engine box
and surrounding area
Refinish companionway ladder
Install latch on engine
instrument panel cover
Complete and install
fiberglass holding tank and associated plumbing
Install Lavac marine toilet
Install electric water pump,
accumulator tank, and potable water plumbing
Install bilge pumps
Install faucets at galley sink
(2--one for potable and manual hand pump for salt)
Install entire electrical
system--batteries to wiring to panels, AC and DC systems
Install electronics
Install Beta Marine BD 722
diesel engine and engine controls
Install fuel, exhaust, and raw
water systems for the engine
Order and install new shafting
and propeller
Complete construction of,
varnish, and install cockpit coamings
Install handrails--exterior
and interior
Install electric anchor
windlass
Install previously-constructed
anchor platform and rollers
Install traveler, genoa
tracks, and other sailing hardware
Install bronze winch stands
and sheet winches
Install mooring cleats and
hardware
Install cockpit shower
connection
Install 30 amp shore power
receptacle
Install boarding ladder
brackets
Order and install lifelines
(double)
Install radar pole and solar
panel mount; hire out welding as required
Inspect rigging and mast to
determine course of action
Paint bottom
Remove old registration
numbers
Have dodger, bimini, and other
canvas made as required
Allowing for the likelihood that some
of the trimwork and other can and will be completed during off-times
between other major projects during the weeks ahead, I anticipate that
the list above will require about one months' shop time, to be completed
in and around the engine installation. |