Holby 26

Boat:

Holby Pilot 19

Schedule:

Project Schedule: April 2022- December 2022 (Non-Continuous)

Project Scope: Remove jet drive and engine and reconfigure for traditional outboard installation; paint hull; sundry related projects TBD

Project Complete:  304.5 Total Hours

Begin Daily Project Logs

May 12, 2022

Holby 26

Thursday

Another round of sanding brought the large bottom patch tantalizingly close to its final shape, with only a few small voids requiring more attention, as well as some additional work needed at the transition to the transom.

The transom portion of the patch grew closer as well, though some fine-tuning remained, particularly at the lower edge,  The adjacent work on the transom, including smaller patches and hole-filling, would continue to be refined as I moved ahead with additional rounds of fairing compound on the transom cutout and environs.

Total time billed on this job today: 2 hours

0600 Weather Observation: 43°, clear with fog. Forecast for the day: Early fog, then clearing and sunny, 81°