Aventura 40

Boat:

Charlotte (FKA Aventura), a 1977 Sea Sprite 23' Sloop

Schedule:

Project Complete:  273.75 Total Hours

Scope of Project: Hull and deck refinish; brightwork maintenance; repairs as necessary; minor interior refit

Begin Daily Project Logs

November 29, 2015

Aventura 40

< Back to Aventura

Sunday

Now that the stem and taffrail pieces were complete and prepared with a sealer coat of varnish, I continued with their final installation.  The taffrail was all set to go, as I’d prepared all the fastener holes during initial fitting, and installation went quickly.

To install the stem, I marked and drilled/tapped all the fastener holes, as usual, and with that complete I installed the wood in a bed of sealant.


Afterwards, I bunged the screw holes.

Finally, I applied a second coat of semi-gloss white enamel to the interior overhead.


Total time billed on this job today:  1.75 Hours

0600 Weather Report:
Clear, 12°.  Forecast for the day:  Sunny, high around 30.