Aventura 16

Boat:

Charlotte (FKA Aventura), a 1977 Sea Sprite 23' Sloop

Schedule:

Project Complete:  273.75 Total Hours

Scope of Project: Hull and deck refinish; brightwork maintenance; repairs as necessary; minor interior refit

Begin Daily Project Logs

October 26, 2015

Aventura 16

< Back to Aventura

Monday

In a short work session after an appointment ran much longer than expected, I managed to complete another round of finish sanding on the deck areas (including four loose hatches), this time with a vibrating finishing sander and 120 grit paper to take care of the fine fairing compound I applied last time, as well as to sand all other areas and get into some of the corners that I’d not yet addressed.

In the immediate future I’d finish up the major deck surface prep with some hand and detail work as required, and do a final assessment of all areas to determine whether any additional work would be required before final high-build primer preparations.

Total time billed on this job today: 2 hours

0600 Weather Report:
30°, clear. Forecast for the day: sunny and breezy, temperatures in the high 40s.