Holby 56

Boat:

Holby Pilot 19

Schedule:

Project Schedule: April 2022- December 2022 (Non-Continuous)

Project Scope: Remove jet drive and engine and reconfigure for traditional outboard installation; paint hull; sundry related projects TBD

Project Complete:  304.5 Total Hours

Begin Daily Project Logs

November 29, 2022

Holby 56

Tuesday

I spent the day removing all the masking from the boat, and otherwise cleaning up and getting the shop back to normal, stowing paint and equipment and so forth.  The unmasking was straightforward but rather time-consuming and fussy on deck, where the paint was still fresh and tape removal required some extra care, exacerbated by the sheer volume of masking and the tight quarters in some areas.

It was nice to see the whole project exposed for the first time since painting began, and I worked on a relatively short list of tasks remaining to complete the work required before calling the job complete.

Total time billed on this job today: 6.5 hours

0600 Weather Observation: 0600 Weather Observation: 27°, clear, dew point 19°. Forecast for the day: Sunny, 37°