Holby 48

Boat:

Holby Pilot 19

Schedule:

Project Schedule: April 2022- December 2022 (Non-Continuous)

Project Scope: Remove jet drive and engine and reconfigure for traditional outboard installation; paint hull; sundry related projects TBD

Project Complete:  304.5 Total Hours

Begin Daily Project Logs

November 8, 2022

Holby 48

Tuesday

After final preparations, over the course of the morning I applied four coats of epoxy-based finish primer to the after cockpit areas (i.e. outboard well) and the hull, leaving the primer to cure overnight.

Total time billed on this job today: 5 hours

0600 Weather Observation: 0600 Weather Observation: 42°, clear, dew point 24°. Forecast for the day: Sunny and windy, 49°