Holby 45

Boat:

Holby Pilot 19

Schedule:

Project Schedule: April 2022- December 2022 (Non-Continuous)

Project Scope: Remove jet drive and engine and reconfigure for traditional outboard installation; paint hull; sundry related projects TBD

Project Complete:  304.5 Total Hours

Begin Daily Project Logs

November 3, 2022

Holby 45

Thursday

After final preparations, I spray-applied three coats of epoxy high-build primer on the new work in the stern, small gelcoat patches, and the hull.

Total time billed on this job today: 4 hours

0600 Weather Observation: 0600 Weather Observation: 31°, clear, dew point 26°. Forecast for the day: Sunny, 61°