Holby 34

Boat:

Holby Pilot 19

Schedule:

Project Schedule: April 2022- December 2022 (Non-Continuous)

Project Scope: Remove jet drive and engine and reconfigure for traditional outboard installation; paint hull; sundry related projects TBD

Project Complete:  304.5 Total Hours

Begin Daily Project Logs

October 13, 2022

Holby 34

Thursday

In a short work day, I sanded as needed the minor epoxy repairs on the hull, then sanded the entire hull once more with 120 grit paper on my 6″ sander, the final round of sanding required for now other than some minor detail and touch-up work.

The next focus would be on completing the installation and fairing/finish work on the new outboard splashwell.  I planned to get started on that in a few days, immediately upon my return from some unrelated business over the next few days.

Total time billed on this job today: 2 hours

0600 Weather Observation: 50°, mainly clear. Forecast for the day: Mainly cloudy, 67°