Halcyon 5

Boat:

Halcyon,  Sailmaster 22 Sloop #128

Schedule:

Project Complete:  294.5 Total hours

Scope of Project:   Full restoration, including deck refinishing and repair; interior refinishing; new electrical and systems; rigging inspection; brightwork maintenance

Begin Daily Project Logs

January 5, 2017

Halcyon 5

< Back to Halcyon

Thursday

I spent the day removing deck hardware, starting at the stem and working my way aft along both sides.  The hardware and fasteners were old and appeared to be original installations in most cases, and many of the fasteners were in poor condition, often breaking off during removal.   Bow pulpit, cleats, anchor hardware, chainplates, running lights…all were among the pieces I removed during a morning’s work.  The aluminum running light housings were in poor condition, and the starboard side fell apart during removal.

I’d continue with the remaining hardware on the aft half of the boat next time.

Total time billed on this job today:  4.5 hours

0600 Weather Observation:
25°, clear.  Forecast for the day:  Mostly sunny, 29°