Halcyon 33

Boat:

Halcyon,  Sailmaster 22 Sloop #128

Schedule:

Project Complete:  294.5 Total hours

Scope of Project:   Full restoration, including deck refinishing and repair; interior refinishing; new electrical and systems; rigging inspection; brightwork maintenance

Begin Daily Project Logs

February 15, 2017

Halcyon 33

< Back to Halcyon

Wednesday

After final preparations, paint mixing, and tacking off, I applied three coats of Alexseal off-white gloss topcoat to the deck areas.   I sprayed the decks in two stages this time (I’d been able to do the primers all at once), to avoid leaning into fresh paint:  first the cockpit well and seating areas, as well as the coachroof and hatch tops, then, after three coats in those areas, I continued with three coats on the cabin trunk channels, and other areas.

Total time billed on this job today:  4.75 hours

0600 Weather Observation:
Mostly clear, 20°.  Forecast for the day:  Snow beginning late in the afternoon, perhaps another 8-12″ overnight.