Halcyon 2

Boat:

Halcyon,  Sailmaster 22 Sloop #128

Schedule:

Project Complete:  294.5 Total hours

Scope of Project:   Full restoration, including deck refinishing and repair; interior refinishing; new electrical and systems; rigging inspection; brightwork maintenance

Begin Daily Project Logs

January 2, 2017

Halcyon 2

< Back to Halcyon

Monday

The owner elected to strip the bottom and start fresh, so I made this my first task.  After setting up and getting ready, I spent the day stripping all the old bottom paint from the starboard side, and a bit over half of the port side.  I removed the bulk of the old paint with a carbide scraper and finished up with two sanding passes and two sanding grits to remove the remnants and finalize the bottom surface.  The substrate was in good condition overall.

I’d finish up the last section next time.

Total time billed on this job today:  8 hours

0600 Weather Observation:
15°, clear.  Forecast for the day:  Sunny, 37°