Halcyon 58

Boat:

Halcyon,  Sailmaster 22 Sloop #128

Schedule:

Project Complete:  294.5 Total hours

Scope of Project:   Full restoration, including deck refinishing and repair; interior refinishing; new electrical and systems; rigging inspection; brightwork maintenance

Begin Daily Project Logs

March 26, 2017

Halcyon 58

< Back to Halcyon

Some small jobs, completed over various days as time and new arrivals dictated:

1.  I secured the new stove to its sliding shelf with four screws through the bottom of the stove housing.

2.  I repositioned the jack stands and painted the bottom patches beneath.

Total time billed on this job today: 1 hour