Halcyon 45

Boat:

Halcyon,  Sailmaster 22 Sloop #128

Schedule:

Project Complete:  294.5 Total hours

Scope of Project:   Full restoration, including deck refinishing and repair; interior refinishing; new electrical and systems; rigging inspection; brightwork maintenance

Begin Daily Project Logs

March 2, 2017

Halcyon 45

< Back to Halcyon

Thursday

With sufficient base coat buildup now on all small parts and the interior trim, I continued the varnish work with a maintenance coat of rubbed-effect satin varnish on all interior surfaces, including shelf trim and bulkheads, along with the berth trim and various loose trim pieces as necessary.

Total time billed on this job today:  2.25 hours

0600 Weather Observation:
40°. mostly cloudy.  Forecast for the day:  clearing, windy, getting colder