Acadia 65

Boat:

Acadia, 1979 Sabre 34

Schedule:

September 2016 – December 2016

Begin Daily Project Logs

March 28, 2017

Acadia 65

< Back to Acadia

Tuesday

With the varnish work on the interior trim and bulkheads looking good, I deemed it complete and removed the masking tape.  I’d give the fresh varnish a little time before taping over it for the next painting steps.

I sanded and revarnished the loose doors and parts in the shop, this time with satin varnish, but found that it dried with substantial gloss for some reason, perhaps because it was a new can of product that I might not have stirred.  So I’d do another coat on those parts next time.

Total time billed on this job today:  2.25 hours

0600 Weather Observation:
32°, cloudy.   Forecast for the day:  cloudy, rain showers later.