Danusia 16

Boat:

Danusia, Cape Dory 31

Schedule:

Project Complete:  234.5 Total Hours

Scope of Project:  Brightwork refinish; cabin sole refinish; miscellaneous maintenance, upgrades, and repairs

Begin Daily Project Logs

January 14, 2016

Danusia 16

< Back to Danusia

Thursday

As usual, I began the day by sanding the brightwork with 320 grit paper, then cleaned up the wood and surrounding decks to prepare for the next coat of varnish later in the day.

Meanwhile, I continued work on the cabin sole.  This time, I stripped the largest section, located in the main cabin.

Afterwards, I applied the third coat of varnish to the exterior brightwork.

Total time billed on this job today:  6.75 hours

0600 Weather Report;
Partly cloudy.  Forecast for the day:  Partly sunny, highs in the 20s