Danusia 12

Boat:

Danusia, Cape Dory 31

Schedule:

Project Complete:  234.5 Total Hours

Scope of Project:  Brightwork refinish; cabin sole refinish; miscellaneous maintenance, upgrades, and repairs

Begin Daily Project Logs

January 8, 2016

Danusia 12

< Back to Danusia

Friday

During the day, I finished up most of the remaining sanding work, starting with the starboard eyebrow trim and coaming, then working around the taffrail before moving on deck to hand-sand the handrails and various coachroof trim.  Later, I sanded the cockpit coamings and surrounding trim, leaving only the hard-to-reach pockets at the forward ends of the coamings for later attention–my hands couldn’t face any more just then.  I’d also have to finish up the anchor platform, which I’d not yet touched.  But the bulk of the prep was complete, for which I was grateful.

Total time billed on this job today:  5.75 hours

0600 Weather Report:
10°, clear.  Forecast for the day:  Sun, then increasing clouds, high in the low 30s