Lively Heels Phase 3-20

Boat:

Lively Heels, a 1976 Fisher 30

Schedule:

Project Schedule:  November 2020 – April 2021

Project Scope:  Reconfigure and simplify engine-based heating system; install woodstove for cabin heating; remove sanitation treatment system and replace with holding tank, conceive and build deck storage boxes; miscellaneous and sundry small projects

Project Complete:  145.75 Total Hours

Begin Daily Project Logs

February 14, 2021

Lively Heels Phase 3-20

Sunday

With the cockpit box securely  glued, I removed the zip ties–most of them slid out, but I cut and abandoned the rest–and then lightly sanded and rounded over all the corners of the box to prepare for fiberglass.  Afterwards, I installed tabbing over all the seams, leaving the field areas for another time since I had no appropriate fiberglass on hand at the moment (it was on the way).

Total time billed on this job today:  1.5 hours

0600 Weather Observation:  15°, cloudy.   Forecast for the day:   Cloudy, 29°