Lively Heels Phase 3-16

Boat:

Lively Heels, a 1976 Fisher 30

Schedule:

Project Schedule:  November 2020 – April 2021

Project Scope:  Reconfigure and simplify engine-based heating system; install woodstove for cabin heating; remove sanitation treatment system and replace with holding tank, conceive and build deck storage boxes; miscellaneous and sundry small projects

Project Complete:  145.75 Total Hours

Begin Daily Project Logs

February 10, 2021

Lively Heels Phase 3-16

Wednesday

After lightly sanding the first round of fairing filler on the deck box, I applied a second layer, this time using a wide trowel to span the entire height of the box.  Because the box was fairly lightweight, I’d noted the last time that  tended to move about when working on the sides, so now I filled it with some scrap lumber to help weight it down; this worked well to allow me to trowel effectively.

Total time billed on this job today:  .75 hours

0600 Weather Observation:  0°, clear, 2″ or so of snow from yesterday.   Forecast for the day:   Sunny, 28°.