Jasmine 43

Boat:

Jasmine, a 1972 Allied Seawind 30' ketch

Schedule:

Project Complete:  431.75 Total Hours

Scope of Project:   Deck core repairs and other deck-related work and refinishing; rigging and chainplate work; electrical overhaul; install Norvane windvane; sundry upgrades and maintenance.  No hull work.

Begin Daily Project Logs

February 2, 2018

Jasmine 43

< Back to Jasmine

Friday

Now that the nonskid painting was complete, I removed all the masking tape, and temporarily replaced some of the hatches I’d removed earlier.

Before continuing with deck work, I wanted to give the fresh paint additional cure time, so I spent a little time working on specifying and preparing orders for some of the items–mainly electrical–that I’d eventually need in the weeks to come, but otherwise meaningful progress on the project would wait till after the weekend.

Total time billed on this job today:  1 hour

0600 Weather Observation:  32°, light snow.  Forecast for the day:  Light snow, another inch or two, then ending in the morning and becoming colder.