Jasmine 38

Boat:

Jasmine, a 1972 Allied Seawind 30' ketch

Schedule:

Project Complete:  431.75 Total Hours

Scope of Project:   Deck core repairs and other deck-related work and refinishing; rigging and chainplate work; electrical overhaul; install Norvane windvane; sundry upgrades and maintenance.  No hull work.

Begin Daily Project Logs

January 26, 2018

Jasmine 38

< Back to Jasmine

Friday

Beginning with the cockpit, then moving on to the sidedecks and foredeck, I wrapped up the deck masking work.  In the cockpit, I left an extra 3/4″ width at the outboard edges of the seats to accommodate the thickness of the coamings once reinstalled, and narrowed the gloss border areas to 3/4″ next to the cockpit locker openings, but in other areas I masked off 1-1/2″ borders, as with the masking I’d done earlier.

With the masking complete, I vacuumed once more, then solvent-washed the exposed areas with the special wipe-down solvent provided by the paint system and other final preparations required so I could apply the gloss topcoats next time.

Total time billed on this job today:  4 hours

0600 Weather Observation:  2°, clear.  Forecast for the day:  Sunny, approaching 20°