Jasmine 34

Boat:

Jasmine, a 1972 Allied Seawind 30' ketch

Schedule:

Project Complete:  431.75 Total Hours

Scope of Project:   Deck core repairs and other deck-related work and refinishing; rigging and chainplate work; electrical overhaul; install Norvane windvane; sundry upgrades and maintenance.  No hull work.

Begin Daily Project Logs

January 22, 2018

Jasmine 34

< Back to Jasmine

Monday

The fine fairing compound had plenty of cure time over the weekend, and now I sanded these areas as needed to remove the excess and complete the high build phase.

During the rest of the day, I cleaned up and prepared the boat and shop:  blow down, vacuum, rinse down the floor,  two rounds of solvent wash, and all other related steps to prepare the decks and loose parts for finish primer next.  As before, I prepared portions of the deck with protective paper for me to walk, kneel, and/or lean on so I could reach and paint the inboardmost areas first.

Total time billed on this job today:  7.5 hours

0600 Weather Observation:  31°, cloudy.  Forecast for the day:  Snow developing in the afternoon and evening, continuing overnight with light amounts