Jasmine 32

Boat:

Jasmine, a 1972 Allied Seawind 30' ketch

Schedule:

Project Complete:  431.75 Total Hours

Scope of Project:   Deck core repairs and other deck-related work and refinishing; rigging and chainplate work; electrical overhaul; install Norvane windvane; sundry upgrades and maintenance.  No hull work.

Begin Daily Project Logs

January 18, 2018

Jasmine 32

< Back to Jasmine

Thursday

I spent the day sanding all deck areas with 220 grit paper, by machine and with lots of handwork in the tight corners, gutters, bulwarks, and other areas.  As expected, the fresh primer highlighted various areas that would require fine-filling, which would be my next step.

Total time billed on this job today:  8 hours

0600 Weather Observation:  10°, clear, about 6″ new snow.  Forecast for the day:  Sunny, 30°