Jasmine 31

Boat:

Jasmine, a 1972 Allied Seawind 30' ketch

Schedule:

Project Complete:  431.75 Total Hours

Scope of Project:   Deck core repairs and other deck-related work and refinishing; rigging and chainplate work; electrical overhaul; install Norvane windvane; sundry upgrades and maintenance.  No hull work.

Begin Daily Project Logs

January 17, 2018

Jasmine 31

< Back to Jasmine

Wednesday

After final preparations, I started the high build application with the coachroof and cockpit well, areas for which I needed to walk, lean, or kneel on the more outboard sections of the deck.  Over the course of a few hours, I applied three coats to these areas, then continued from the staging with three coats on the remainder of the decks and loose hatches.

Total time billed on this job today:  6 hours

0600 Weather Observation:  25°, snow.  Forecast for the day:  Snow, 4-8″, around 28°