Jasmine 13

Boat:

Jasmine, a 1972 Allied Seawind 30' ketch

Schedule:

Project Complete:  431.75 Total Hours

Scope of Project:   Deck core repairs and other deck-related work and refinishing; rigging and chainplate work; electrical overhaul; install Norvane windvane; sundry upgrades and maintenance.  No hull work.

Begin Daily Project Logs

December 19, 2017

Jasmine 13

< Back to Jasmine

Tuesday

To begin, I unloaded the sandbags from the newly-laid core on the sidedecks and elsewhere, exposing the new core.

I had other commitments away from the shop later in the day, so with only a limited amount of time I chose to focus on the new core installation at the poop deck.  After final preparations, I installed the core in the same manner as the rest of the deck.

Total time billed on this job today:  1.75 hours

0600 Weather Observation:  Clear, 20°, 4-5″ snow yesterday afternoon and overnight.  Forecast for the day:  Clouds and sun, near 40