Lively Heels Phase 3-35

Boat:

Lively Heels, a 1976 Fisher 30

Schedule:

Project Schedule:  November 2020 – April 2021

Project Scope:  Reconfigure and simplify engine-based heating system; install woodstove for cabin heating; remove sanitation treatment system and replace with holding tank, conceive and build deck storage boxes; miscellaneous and sundry small projects

Project Complete:  145.75 Total Hours

Begin Daily Project Logs

March 26, 2021

Lively Heels Phase 3-35

Friday

As a final step before the final paint work, I laid out and masked off the field areas of the two lids to protect the eventual nonskid areas from overspray.  Afterwards, I solvent-washed all the pieces and parts and wiped with a tack rag.

Over the course of the remaining morning, I spray-applied three coats of snow white gloss topcoat to the boxes and lids, which paint matched the existing on the deck areas.

Total time billed on this job today:  2 hours

0600 Weather Observation:  45°, foggy.  Forecast for the day:   Fog and rain, 56°