Lively Heels Phase 3-34

Boat:

Lively Heels, a 1976 Fisher 30

Schedule:

Project Schedule:  November 2020 – April 2021

Project Scope:  Reconfigure and simplify engine-based heating system; install woodstove for cabin heating; remove sanitation treatment system and replace with holding tank, conceive and build deck storage boxes; miscellaneous and sundry small projects

Project Complete:  145.75 Total Hours

Begin Daily Project Logs

March 25, 2021

Lively Heels Phase 3-34

Thursday

After a light round of sanding with 320 grit paper by machine and hand, the deck boxes were ready for the next steps, which included some minor masking on the lids before gloss topcoats.  Since the primer hadn’t yet had the minimum 24 hours to cure before masking atop the fresh paint, I completed all the setup I could for the work ahead, including a thorough cleanup of the shop and surrounding areas, then worked on other things during the remainder of the day.

Total time billed on this job today:  1 hour 

0600 Weather Observation:  44°, foggy.  Forecast for the day:   Mostly cloudy, 56°